AP Samagra Shiksha: 40% Advance Funds Released for School Infrastructure Works (2025-26)
Procs. Rc.No. SS-13026/20/2025-CIVIL SEC-SSA, Dt: 28-08-2025
Sub: APSS – Civil Works – Strengthening of Existing Schools “Rejuvenation of Basic Infrastructure and over all Cleanliness of Government Schools” (Elementary)(NR)–Release of 40% advance amount to the DPO accounts– Sanction accorded-Reg.
Ref: T/o Procgs. Rc. No. SS-13026/20/2025-CIVIL-SEC-SSA Date: 29-03-2025.
1) In the reference cited, administrative sanction was accorded for providing Boundary Walls, Boys Toilets, Girls Toilets, Electrification and Major Repairs under the Non-Recurring Budget of the BIGs Programme (“Rejuvenation of Basic Infrastructure and Overall Cleanliness of Government Schools”). The sanction covered a total of 1000 physical units with a financial allocation of Rs. 6134.18 lakhs.
2) To facilitate procurement of essential materials such as steel, sand, stone, cement, etc., and to enable grounding of the works, it is proposed by the State Project Engineer, APSS to release an amount of Rs. 21,10,19,000/- (Rupees Twenty-One Crores Ten Lakhs Nineteen Thousand only) as 1st instalment advance as per Samagra Shiksha norms.
3) Accordingly, under the powers vested with the State Project Director, Samagra Shiksha, sanction is hereby accorded for release of Rs. 21,10,19,000/- (Rupees Twenty One Crores Ten Lakhs Nineteen Thousands only) as 1st instalment advance, duly adjusting against the budget allocation available for the spillover civil works sanctioned in AWP&B 2025-26.
4) The intervention-wise and district-wise details of fund release are furnished in the annexure appended to this order.
5) Accordingly, the Finance Controller, Office of the State Project Director, Samagra Shiksha, is instructed to release an amount of Rs. 21,10,19,000/- (Rupees Twenty-One Crores Ten Lakhs Nineteen Thousand only) to the District Project Office accounts of the respective districts for Civil Works as indicated in Table–I above, under the budget head:
Elementary Education – 2. Strengthening of Existing Schools
Intervention 2.3: Rejuvenation of Basic Infrastructure and Overall Cleanliness of Government Schools (Elementary) (NR)
Approved Spillover – AWP&B 2025-26
6) The above release of 40% advance is intended to enable timely initiation and execution of works. The works shall be executed through the respective School Management Committees (SMCs).
7) The District Educational Officers / Additional Project Coordinators, Executive Engineers, and FAOs are instructed to:
Utilize the funds exclusively for the approved spillover works sanctioned under AWP&B 2025- 26, without any deviation.
Ensure that diversion or misutilization of funds for any other purpose will be viewed seriously.
Procs. Rc.No. SS-13026/20/2025-CIVIL SEC-SSA, Dt: 28-08-2025
Sub: APSS – Civil Works – Strengthening of Existing Schools “Rejuvenation of Basic Infrastructure and over all Cleanliness of Government Schools” (Elementary)(NR)–Release of 40% advance amount to the DPO accounts– Sanction accorded-Reg.
Ref: T/o Procgs. Rc. No. SS-13026/20/2025-CIVIL-SEC-SSA Date: 29-03-2025.
AP Samagra Shiksha: 40% Advance Funds Released for School Infrastructure Works (2025-26)
SANCTION ORDER1) In the reference cited, administrative sanction was accorded for providing Boundary Walls, Boys Toilets, Girls Toilets, Electrification and Major Repairs under the Non-Recurring Budget of the BIGs Programme (“Rejuvenation of Basic Infrastructure and Overall Cleanliness of Government Schools”). The sanction covered a total of 1000 physical units with a financial allocation of Rs. 6134.18 lakhs.
2) To facilitate procurement of essential materials such as steel, sand, stone, cement, etc., and to enable grounding of the works, it is proposed by the State Project Engineer, APSS to release an amount of Rs. 21,10,19,000/- (Rupees Twenty-One Crores Ten Lakhs Nineteen Thousand only) as 1st instalment advance as per Samagra Shiksha norms.
3) Accordingly, under the powers vested with the State Project Director, Samagra Shiksha, sanction is hereby accorded for release of Rs. 21,10,19,000/- (Rupees Twenty One Crores Ten Lakhs Nineteen Thousands only) as 1st instalment advance, duly adjusting against the budget allocation available for the spillover civil works sanctioned in AWP&B 2025-26.
4) The intervention-wise and district-wise details of fund release are furnished in the annexure appended to this order.
| Intervention | Phy | Financial |
40% Amount proposed to
Release |
| Boys toilets | 123 | 467.40 |
186.96 |
| Girls toilets | 139 | 528.20 |
211.28 |
| Electrification | 140 | 210.00 |
84.00 |
| Boundary walls | 354 | 3331.88 |
1332.75 |
| Major repairs | 123 | 738.00 |
295.20 |
| Total | 879 5275.48 |
2110.19 |
Note: The component wise District Wise allotments tables are in the PDF below
5) Accordingly, the Finance Controller, Office of the State Project Director, Samagra Shiksha, is instructed to release an amount of Rs. 21,10,19,000/- (Rupees Twenty-One Crores Ten Lakhs Nineteen Thousand only) to the District Project Office accounts of the respective districts for Civil Works as indicated in Table–I above, under the budget head:
Elementary Education – 2. Strengthening of Existing Schools
Intervention 2.3: Rejuvenation of Basic Infrastructure and Overall Cleanliness of Government Schools (Elementary) (NR)
Approved Spillover – AWP&B 2025-26
6) The above release of 40% advance is intended to enable timely initiation and execution of works. The works shall be executed through the respective School Management Committees (SMCs).
7) The District Educational Officers / Additional Project Coordinators, Executive Engineers, and FAOs are instructed to:
Utilize the funds exclusively for the approved spillover works sanctioned under AWP&B 2025- 26, without any deviation.
Ensure that diversion or misutilization of funds for any other purpose will be viewed seriously.
8) The Executive Engineers, APSS shall:
Submit the technically sanctioned estimates to the respective School Management Committees within one week from the date of receipt of this order, prior to commencement of execution. Oversee and certify the execution of works as per estimates.
Furnish Utilization Certificates (UCs) for the completed portion of works to enable release of the 2nd instalment.
9) The District Educational Officers / Additional Project Coordinators, Executive Engineers, and School Management Committees (SMCs) are hereby instructed to:
Complete the works strictly as per Civil Works Codal Rules and Samagra Shiksha norms within a period of three (3) months from the date of receipt of this order. Ensure quality and timely completion of works.
10) The Finance Wing of the DPOs shall retain all original bills and vouchers for submission to Internal Audit, Statutory Audit, and Accountant General (AG) Audit Teams, as and when required.
Submit the technically sanctioned estimates to the respective School Management Committees within one week from the date of receipt of this order, prior to commencement of execution. Oversee and certify the execution of works as per estimates.
Furnish Utilization Certificates (UCs) for the completed portion of works to enable release of the 2nd instalment.
9) The District Educational Officers / Additional Project Coordinators, Executive Engineers, and School Management Committees (SMCs) are hereby instructed to:
Complete the works strictly as per Civil Works Codal Rules and Samagra Shiksha norms within a period of three (3) months from the date of receipt of this order. Ensure quality and timely completion of works.
10) The Finance Wing of the DPOs shall retain all original bills and vouchers for submission to Internal Audit, Statutory Audit, and Accountant General (AG) Audit Teams, as and when required.
పాఠశాల మౌలిక వసతుల పనులకు మంజూరు ఉత్తర్వుల సారాంశం
ఈ పత్రం, ఆంధ్రప్రదేశ్ సమగ్ర శిక్షా రాష్ట్ర ప్రాజెక్ట్ డైరెక్టర్ జారీ చేసిన మంజూరు ఉత్తర్వు. ప్రభుత్వ పాఠశాలల్లో మౌలిక సదుపాయాలు మరియు పరిశుభ్రత పెంపుదల ("Rejuvenation of Basic Infrastructure and Overall Cleanliness of Government Schools," ఎలిమెంటరీ, పునరావృతం కాని బడ్జెట్ - NR) కోసం ఉద్దేశించిన కార్యక్రమం కింద సివిల్ పనుల కోసం మొదటి విడత అడ్వాన్స్ నిధులను విడుదల చేయడానికి ఈ ఉత్తర్వులు జారీ చేయబడ్డాయి.
ముఖ్య ఆర్థిక మరియు కార్యక్రమ వివరాలు
మొత్తం మంజూరైన అడ్వాన్స్: రూ. 21,10,19,000 (రూపాయలు ఇరవై ఒక్క కోట్ల పది లక్షల పంతొమ్మిది వేలు మాత్రమే).
ఉద్దేశం: ఉక్కు, ఇసుక, రాయి, సిమెంట్ మొదలైన ముఖ్యమైన సామాగ్రిని సేకరించడానికి మరియు పనులను ప్రారంభించడానికి (grounding of works) ఈ 40% మొదటి విడత అడ్వాన్స్ విడుదల చేయబడింది.
మొత్తం అడ్వాన్స్ మొత్తం: ₹21,10,19,000 (రూ. 21.10 కోట్లు)
శాతం: మొదటి విడతగా 40% అడ్వాన్స్
మొత్తం ప్రాజెక్ట్ విలువ: ₹52.75 కోట్లు (5275.48 లక్షలు)
జిల్లా వారీ కవరేజీ
ఆంధ్రప్రదేశ్లో 26 జిల్లాలు
879 పాఠశాలలు కవర్ చేయబడతాయి
అత్యధిక కేటాయింపు ఉన్న జిల్లాలు:
శ్రీకాకుళం: ₹288.53 లక్షలు
కోనసీమ: ₹242.08 లక్షలు
బాపట్ల: ₹223.82 లక్షలు
879 పాఠశాలలు కవర్ చేయబడతాయి
అత్యధిక కేటాయింపు ఉన్న జిల్లాలు:
శ్రీకాకుళం: ₹288.53 లక్షలు
కోనసీమ: ₹242.08 లక్షలు
బాపట్ల: ₹223.82 లక్షలు
బడ్జెట్ శీర్షిక: ఈ నిధులు ఎలిమెంటరీ ఎడ్యుకేషన్ - 2. బలహీనంగా ఉన్న పాఠశాలల బలోపేతం (Strengthening of Existing Schools) , కింద AWP&B 2025-26 లో మంజూరు చేయబడిన మిగిలిపోయిన (spillover) సివిల్ పనుల కోసం కేటాయించబడ్డాయి
అమలు ఆదేశాలు మరియు గడువు
నిర్వహణ బాధ్యత: ఈ పనులను సంబంధిత పాఠశాల నిర్వహణ కమిటీల (SMCs) ద్వారా నిర్వహించాలి.
గడువు: ఈ ఉత్తర్వులు అందిన తేదీ నుండి మూడు (3) నెలల కాలంలోపు పనులను పూర్తి చేయాలి. నాణ్యత మరియు సకాలంలో పూర్తి చేయడం తప్పనిసరి.
నిబంధనలు: నిధులను అనుమతించబడిన స్పిల్ఓవర్ పనులకే ఉపయోగించాలి. ఇతర ప్రయోజనాల కోసం నిధులను దారి మళ్లించడం లేదా దుర్వినియోగం చేయడం తీవ్రంగా పరిగణించబడుతుంది.
పనుల పూర్తి కాల వ్యవధి
పూర్తి చేసే కాలం: ఉత్తర్వు అందిన తేదీ నుండి 3 నెలలు
పనులు పాఠశాల నిర్వహణ కమిటీల (SMCs) ద్వారా నిర్వహించబడతాయి
కార్యనిర్వాహక ఇంజనీర్ల బాధ్యతలు (Executive Engineers):
పనులు ప్రారంభించడానికి ముందు, ఈ ఉత్తర్వులు అందిన తేదీ నుండి ఒక వారంలోపు సాంకేతికంగా మంజూరైన అంచనాలను (technically sanctioned estimates) SMC లకు సమర్పించాలి.
అంచనాల ప్రకారం పనుల అమలును పర్యవేక్షించి, ధృవీకరించాలి.
రెండవ విడత నిధులు విడుదల చేయడానికి వీలుగా, పూర్తయిన పనులకు సంబంధించిన వినియోగ ధృవపత్రాలను (Utilization Certificates - UCs) సమర్పించాలి.